…Functions / …Real Time Alarms / …Real Time Alarm 1 (2)
On hour
Sets the hour the alarm is activated – not applicable if Every Hour (see page 89) is set to On.
On minute
Set the minutes past the hour the alarm is activated.
Duration
Set the duration the alarm is active.
Display enable
If disabled (Off), the alarm state does not appear in the operator level diagnostics window or
the alarm log
Tag
A 16-character alphanumeric tag displayed as a diagnostic message that appears in the
Diagnostic Status Bar and the Diagnostic View in the Operator Level – see Section 5, page 22.
Bank Control Bank control functionality allows a bank of output devices such as pumps, heaters or
fans to be scheduled On and Off under a duty / assist strategy.
If required one of two different wear levelling schedules can be selected, rotate or
FIFO (First In First Out).
Up to 6 stages may be configured for bank control, each of which can be assigned to a
relay or digital output. Each stage has an associated On trip value, Off trip value and
initial Output. All stages included in a wear levelling schedule must use the same
schedule type (Rotate or FIFO).
The example (overleaf) illustrates how the two modes operate to achieve wear levelling of
3 pumps in a duty / assist strategy.