7.1.2 Starting up the unit for the first time
1.
Follow the instructions on commissioning, see Chapter 7.1.1 Checks before
each commissioning, Page 59.
2.
Turn the compressor over by hand using the flywheel to check that all compo-
nents are capable of moving freely.
3.
Check all fixing screws for tightness. If needed, re-tighten them with the speci-
fied torque.
4.
Check all screwed pipe fittings for leaks. If needed, re-tighten them with the
specified torque.
5.
Make sure that the rotation direction of the motor is correct, see Chap-
ter 7.1.4 Checking the direction of rotation of the motor, Page 62.
Fig. 14 Plug of solenoid valve coil
1 Screw to pull out the plug
6.
Remove the plug from the solenoid valve coil and allow the compressor to run
with open condensate drain valves for 10 minutes in order to ensure perfect
lubrication before starting to build up the pressure.
7.
After 10 minutes, fit the plug of the solenoid valve coil again.
8.
Observe the pressure build-up in the unit properly. If there are any irregulari-
ties, switch off the unit immediately and locate and rectify any errors or get in
touch with the BAUER customer service department, see Chapter 1.2.7 Con-
tact data BAUER KOMPRESSOREN, Page 13.