3. Preparing for Installation
This section provides instructions for transporting, inspecting, and unpacking
the equipment for an Evolution IP-20LH system prior to installation.
3.1 Transportation/Storage
The equipment cases are prepared for shipment by air, truck, railway and sea,
suitable for handling by forklift trucks and slings. The cargo must be kept dry
during transport and storage.
For sea-transport, deck-side shipment is not permitted. Carrier-owned cargo
containers should be used.
It is recommended that the equipment is transported to the installation site in
its original packing cases.
If any intermediate storing is required, all cases must be stored under dry and
cool conditions and out of direct sunlight.
3.2 Inspection
Check the packing lists and ensure that correct parts numbers quantities of
goods have arrived.
Inspect for any damage on the cases and equipment. Report any damage or
discrepancy to a Ceragon representative, by e-mail or fax.
3.3 Unpacking Equipment at the Site
The equipment is packed in sealed plastic bags and moisture absorbing bags
are inserted. Any separate sensitive product, i.e. printed boards, are packed in
anti-static handling bags. The equipment is further packed in special designed
cases.
Marking is done according to standard practice unless otherwise specified by
customers.
Customers address
Contract No
Site name (if known)
Case No
Dimensions and weight of each case are specified in the packing specification
issued for the respective shipment.
Caution!
It is essential that whenever unpacking or disassembling the equipment and
handling printed circuit boards, special precautions should be taken to avoid
ESD (Electrostatic Static Discharge). Generally, units with static discharge
protection should not be unpacked until the installation takes place.
Ensure you are properly grounded at a controlled ESD point before and during
unpacking and handling of any sensitive component.