14 Operation
4 Operation
The Condair RM steam humidier may be commissioned and operated only by persons familiar with the
Condair RM steam humidier and adequately qualied. It is the owner’s responsibility to verify proper
qualication of the personnel.
4.1 First-time commissioning
The rst-time commissioning must always be done by a service technician of your Condair representative
or a well trained and authorised person of the customer. Therefore the current manual does not provide
detailed information on this procedure.
The following steps are carried out upon rst-time commissioning in the specied order:
• Inspecting the steam humidier for correct installation.
• Inspecting the electrical installation
• Inspecting the water installation
• Inspecting the steam installation
• Flushing and deaerating the water supply line
• Determining the carbonate hardness of the supply water (by measurement or from the local water
supplier)
• Conguring the control software of the Condair RM via the RM Display (see chapter 6.1).
• Carrying out test runs including checking of the control and monitoring devices.
• Filling out the commissioning record.