Hand Over to Customer SiE33-102
96 General Information
6. Hand Over to Customer
6.1 Operational Steps
Important Points a) The measurements taken during the test run should be recorded and kept on a test run inspection
sheet.
b) Do not forget to record the length of the refrigerant piping and the refrigerant additional charging
volume on the plate on the back of the outdoor unit external notice board, as this information will be
required for servicing the system.
c) Explain to the customer how to operate the equipment and let him try it.
d) Assemble all the relevant diagrams and other printed matter which is required to operate the system
and hand it all over to the customer (on the spot) and tell him to keep it.
e) Make the service contact address clear.
Complete test run
Make final report
(test run
inspection sheet)
Explain how to
operate
equipment
Hand over
relevant printed
materials
(V1050)
Si33-102.book Page 96 Tuesday, June 26, 2001 3:18 PM
Все каталоги и инструкции здесь: http://splitoff.ru/tehn-doc.html

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Daikin VRV System R-22 PLUS Series and is the answer not in the manual?

Daikin VRV System R-22 PLUS Series Specifications

General IconGeneral
BrandDaikin
ModelVRV System R-22 PLUS Series
CategoryAir Conditioner
LanguageEnglish

Related product manuals