Maximum distances / Bus cable lengths
According to the IEC 61158-2 standard the maximum cable
length of a bus segment with cable type “A” is as follows
(a following in Table 4):
Table 4: Cable lengths
Operating the device Putting the PROFIBUS-DPV1 interface into operation
The following steps are necessary to commission the
interface:
X Connect the NZM-XDMI-DPV1 via the “EASY-Link”
connector with the DMI (basic unit).
You must slide up the cover flap on the right-hand side of
the device in order to plug in the connector on the DMI.
X Connect the 24 V DC power supply for the interface
(Caution! Do not switch on yet!).
X Connect the Profibus plug to the device and switch on the
bus terminator if necessary.
X Switch on the supply voltage for the DMI and interface.
Baud rate [kBit/s] Max. cable length [m]
9.6 1200
19.2 1200
93.75
1200
187.5 1000
500 400
1500 200
3000 100
6000 100
12000 100