2 Installation
2.2 Install field bus
12 CANopen for DA1, DC1, DE11 09/16 MN040019EN www.eaton.com
2.2 Install field bus
When installing the connection, make sure that the control and signal cables
(0 - 10 V, 4 - 20 mA, 24 VDC, etc.), as well as the field bus system‘s
CANopen connection cables, are not routed directly parallel to mains
connection or motor connection cables conveying power.
With parallel cable routing, the clearances between control, signal and field
bus cables ② and energy-carrying mains and motor cables ① must be
greater than 30 cm. Cables should always intersect at right angles.
Figure 3: Routing cables for CANopen ② and mains/motor cables ①
If the system requires a parallel routing in cable ducts, a partition must be
installed between the fieldbus cable ② and the mains and motor cable ①,
in order to prevent electromagnetic interference on the fieldbus.
Figure 4: Separate routing in the cable duct
c Mains and motor connection cable
d CANopen cable
→
Never lay the cable of a field bus system directly parallel to the
energy carrying cables.