Connection of the instrument 16
Manual econ sens3 Version 3.0
2.) Protection of voltage measurement inputs
3.) Measuring voltages and measuring currents must originate from the same network.
4.) Synchronous phase connection
Phases must be connected in the same sequence as the terminals, as the terminal
assignments cannot be changed in the software parameterization.
Caution!
Unprotected voltage measurement inputs can lead to damage to the instrument and
system. Secure the instrument at all times with an IEC approved 10A fuse, an IEC
approved 10A circuit breaker, or additional safety device.