EMC VNX5500 File Installation Guide
Installing Control Stations and extension cables
Ensure that you install the correct Control Station. CS0 should be installed before CS1,
remembering the location of CS0 when you removed it from the mini-rack.
1. Slide the primary Control Station (CS0) into the lowest slot above the DPE as shown in
Figure 11 on page 23.
2. Attach, but do not tighten, the bezel brackets by inserting the screws through the brackets,
the Control Station, the cabinet rail, and into the gang rail.
3. Connect the extension cables after the Control Station has been installed into the ganged rail.
Note: Connect the CS0 B extension cable to the RJ-45 connector (labeled on the CS) and
connect the CS0 MGMT extension cable to the RJ-45 connector (labeled on the CS).
4. Repeat steps 1-3 if a secondary (optional) Control Station (CS1) was shipped with your order.
The extension cables will be labeled CS1.
Note: Connect the CS1 B extension cable to the RJ-45 connector (labeled on the CS) and
connect the CS1 MGMT extension cable to the RJ-45 connector (labeled on the CS).
B