MODEL 1000 SEP 2005
INSTALLATION AND SETUP
3-31
(4) Connect sample gas stream(s) to Analyzer. (DO NOT TURN ON GAS AT THIS TIME.)
(a) Use 1/8-inch or 1/4-inch stainless steel tubing to conduct calibration standard gas.
(b) Ensure that pressure of sample line is regulated to maintain 15-30 psig ±10%.
(c) Sample gas stream inlet(s) are identified in the applicable Sample Conditioning
System ("S.C.S") drawing in the Analyzer drawings addendum to this manual. (See
drawings CE-16120, CE-16220, CE-16320, CE-16420, or CE-16520.)
(5) After all lines have been installed, proceed with Controller wiring connections (see next
section).
(a) Leak check procedures for the GC sample and gas lines are given in Section 3.5.1,
this manual. They require AC power to be turned on at the Analyzer.