Document number: ED.03783.00.001.ENG rev 4 Page 52 of 153
5 How to install the system
This chapter describes
• how to hoist put the several parts of the system,
• and how to assemble the system.
Fully complete the checklist as given in Appendix B “Checklist for installing the system”.
5.1 How to hoist the parts of the system
5.1.1 Unit
At the front and one at the rear of each unit hoisting lugs are mounted on a lifting frame.
Use them to hoist the unit. The JS500 can be hoisted using the hoisting points in the Base
Frame of the unit or by using the forklift tubes in the Base Frame.
The length of the applied slings or chains has to be larger than 1.5 meter.