the cutting band.
u Manually turn the top pulley clockwise approx. 5-10 x to centre the
cutting band on both pulleys. During this process pay attention to
correct running of the pulleys and the cutting band guides!
u Close the doors.
u Carefully move the work plate along the cutting band and place in
the work table tray.
Checking
cutting band
guides
Band guide, top
u Open the top door.
u Check the top cutting band guide for damage.
Cutting band guide, work table
u Check the cutting band guide of the work table for damage.
u Check the cutting band guide of the work table for correct seating in
the work table.
Cutting band flushing, bottom
u Open the bottom door.
u Check the bottom cutting band guide of the band flushing for
damage.
Remove foreign
bodies
Drain pan
u Open the bottom door.
u If necessary remove foreign bodies.
9.2 Weekly maintenance
Checking the
cooling water
flow
Cooling water system
u Open the top door.
u Open the water supply.
u Open the cooling water control.
u Check the cooling water flow rate at the top cutting band guide.
Checking the
flush water flow
Flush water system
u Open the bottom door.
Attention! On opening the control, water will splash horizontally out of
the saw!
u Open the water supply.
u Open the flush water control.
u Check the flush water flow rate at the bottom cutting band guide.