7.2.2.2 Lubricant table
Lubrication
ex works
Specifica-
tions
Lubricant
quantity
Location of ap-
plication
Cate-
gory
Elkalub FLC 8
H1
Cannot be
determined
Lubrication system
FlexxPump: Pre-lu-
bricating rails and
racks
Oil
Güdel H1 NSF
no. 146621
Cannot be
determined
Lubrication system
FlexxPump
Oil
Rivolta F.L.125
Cannot be
determined
Lubrication system
FlexxPump
Oil
Rivolta F.L.500
Cannot be
determined
Lubrication system
FlexxPump
Oil
This table does not purport to be exhaustive.
Tab.7-6 Lubricant table
7.3 Maintenance tasks
7.3.1 Maintenance intervals
The product is subject to natural wear and tear. It wears out, which can cause
unscheduled downtimes of your system. Güdel defines the service life and
maintenance intervals of the product to ensure safe, uninterrupted operation.
Operating hours
Güdel always uses Power On as the operating time for the maintenance inter-
val indicators. Power On shows the duration in which the drives are located
in the control system.
Maintenance OPERATING MANUAL Lubrication system FlexxPump4D