2.1 Document Preparations
This section describes the reference documents that must be ready before the installation.
l Before the installation, you must familiar with the following reference documents:
– BTS3900L (Ver.C) Hardware Description
– Safety Information
l During the installation, you must familiar with the following reference document:
– Installation Reference
2.2 Preparing Tools and Meters
This section describes the tools and meters that are required before installation.
Marking pen
Phillips screwdriver (M3 to
M6)
Flat-head screwdriver (M3 to
M6)
Diagonal pliers
Combination wrench
(capacity 32 mm)
Socket wrench Torque wrench
Power cable crimping tool RJ11 crimping tool Cable cutter
Rubber mallet Soldering iron Wire stripper
Hammer drill (Ø16) Heat gun Level
BTS3900L (Ver.C)
Installation Guide 2 Preparing for Installation
Issue 07 (2013-11-08) Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
6