Figure 11-10 Binding cables on the right side
(1) Transmission cables and signal
cables
(2) CPRI fiber optic cable
(3) Jumpers on the right side (4) Not defined
11.3 Installing the Power Cables
This chapter describes the procedures for installing the power cables and precautions to be taken
during the procedures in the standard power scenario and small configuration scenario.
11.3.1 Standard Powering Scenario
In the case of full configuration with 12 RFUs, connect the input power cables and supply the
power to the cabinet.
Context
By default, 2 X 160A or 4 X 80A should be provided for BTS3900L(Ver.C) cabinet, as shown
in Figure 11-11.
BTS3900L (Ver.C)
Installation Guide
11 Installing the Cables
Issue 07 (2013-11-08) Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
72