Figure 8-8 Secure the temperature probe
Step 4 Connect the electric heating belt and temperature probe to the controller.
Figure 8-9 Wiring diagram
Step 5 Install thermal insulation foam on pipes.
NO TE
Wrap the electric heating belt before wrapping the thermal insulation foam, and the
thermal insulation foam covers the electric heating belt. Verify that the thermal insulation
foam can withstand a temperature greater than or equal to 200°C.
----End