Figure 8-27 Cable interconnection position
Step 7 Install the electromagnetic valve.
NO TE
Do not install the electromagnetic valve when installing the re cylinder for the rst time. Install
the electromagnetic valve when commissioning the
re extinguishing system.
1. Remove the protective cover at the electromagnetic valve installation position
on the container valve. Align the electromagnetic valve and the container
valve, and tighten the electromagnetic valve clockwise.
Figure 8-28 Removing the electromagnetic valve protective cover
----End
FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario) 8 Installing Devices Inside the Pre-fab. Module
Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd. 89