Figure 5-36 Installing battery modules and ller panels (7+7 and 7+0 scenarios)
Figure 5-37 Installing battery modules and ller panels (6+6 and 6+0 scenarios)
Step 3 Open the front cover of a battery module, install the bae plate, and tighten the
two screws. Check the insulation performance of battery modules. Set a
multimeter to the DC voltage mode and measure the voltage between the positive
and negative terminals of each battery module and the screws on the battery
bae plate respectively. If the readings are less than 6 V DC, the insulation is
good. Otherwise, contact technical support engineers.
SmartLi 3.0
User Manual (Short-Term Backup Power) 5 Installation and Cable Connection
Issue 10 (2024-01-31) Copyright © Huawei Digital Power Technologies Co., Ltd. 88