Page 165
User Guide v 1.0 — August 2018 Altanium Neo5
15.5.1 Installing Neo5 on the Mobile Stand
The Neo5 mobile stand and controller come as separate pieces and must be assembled.
1. Carefully place the Neo5 controller on its side to locate and remove the 4x leveling pads.
These pads are hand tight and do not require any tools for removal.
WARNING!
Electrical and mechanical hazard - risk of serious injury and/or damage to the
equipment. Turn off all power to the system and disconnect it completely from the
main input power. Follow the local Lock Out Tag Out procedures.