6. Connect the cables to the appropriate ports on the server canister operator panels and the jacks for
the power modules. Do not connect the power cords to a power module now.
7. Starting with the thickest gauge cable rst, run each cable through the loops on the CMA.
8. Test the CMA to ensure smooth operation. Ensure that the cables do not have pinching or bindings.
Note: When you pull the enclosure from the rack, the rails lock in the serviceable position. To
release the rails from the serviceable position, press the release tab on each inner member rail and
simultaneously push the enclosure into the rack.
Chapter 4. Installing53