Intergas Heating Ltd 48
10. SERVICING THE BOILER
The appliance and the installation should be checked and if necessary cleaned
every year by a registered expert.
For assembly and disassembly the following tools can be used:
4. Cross head screwdriver
5. Allen key 8 mm
6. Fork spanner 30 mm
After servicing, complete the relevant Benchmark Service Record section located
on page of this document.
CAUTION
Work on gas carrying parts may only be carried out by an authorised
installer.
When the appliance has just been operating parts may be hot.
CAUTION
The integrated insolation and burner seal contain ceramic
fibres.

Table of Contents

Other manuals for Intergas Rapid 25

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Intergas Rapid 25 and is the answer not in the manual?

Intergas Rapid 25 Specifications

General IconGeneral
Boiler TypeCombi
DHW Output25 kW
Efficiency Rating93%
Flow Rate10.2 l/min
MountingWall Mounted
ERP EfficiencyA
Max Gas Rate2.78 m³/h
Dimensions (H x W x D)590 x 450 x 240 mm