11 
7. Check that the installation conforms to the instructions in user’s manual. The drive must 
be installed in an upright position. 
8.  Check  that  the  external  connection  terminals  are  tightly  fastened  and  the  torque  is 
appropriate. 
9. Check that there are no screws, cables and other conductive items left in the inverter. If 
not, get them out.   
2.6 Basic commission 
Complete the basic commissioning as followings before actual utilization:     
1.  Select  the  motor  type,  set  correct  motor  parameters  and  select  control  mode  of  the 
inverter according to the actual motor parameters. 
2. Autotune. If possible, de-coupled from the motor load to start dynamic autotune. Or if not, 
static autotune is available.   
3. Adjust the ACC/DEC time according to the actual running of the load.   
4. Commission the device via jogging and check that the rotation direction is as required. If 
not, change the rotation direction by changing the wiring of motor.     
5. Set all control parameters and then operate.