74
3
© 2018 KOSTAL Solar Electric GmbH
Installation
23. Press the right arrow key to go to the next installation
item.
P
The "Country/guideline" menu appears on the
display.
24. Select country or guideline used. Confirm the entries
with “ENTER”.
25. Press the right arrow key to go to the next installation
item.
P
“Accept settings” appears on the display.
26. Press “ENTER” to accept the input.
P
The settings are assumed by the inverter.
P
The inverter restarts after the installation.
H
The inverter is in operation and can now be used.
Initial commissioning is completed.
INFO
If an incorrect country setting has
been selected, this can be re-
assigned under the inverter's menu
item for resetting national guideline.
INFO
If there is an update available for the
inverter, install this first.
INFO
In France, the installer is personally
responsible for obtaining any addi-
tional prescribed labels as required
and attaching them to the inverter
and feed cables.