– “Safety” on page iii
– “Installation Guidelines” on page 51
• Power off the server and peripheral devices and disconnect the power cords and all external cables. See
“Power off the server” on page 11.
• If the server is installed in a rack, remove the server from the rack.
Watch the procedure
A video of this procedure is available at YouTube:
https://www.youtube.com/playlist?list=PLYV5R7hVcs-
BPZOAqQMD37KjuxaVHVBkH
.
Procedure
Step 1. Make preparations for this task.
a. Remove the top cover. See
“Remove the top cover” on page 132.
b. Disconnect the front operator panel cables from the system board. See
“Front panel cable
routing” on page 35
.
Step 2. Remove the two screws that secure the front operator panel.
Figure 71. Front operator panel removal
Step 3. Pull out the front operator panel from the server.
Figure 72. Front operator panel removal
84 ThinkSystem SR250 V2 Maintenance Manual