Lucent Technologies -48V CPS4000/CPS4000 PLUS Cabinet Power System
5 - 24 Installation and Testing Issue 13 December 2000
Initial Start-up and Test
Checklist Refer to Section 7 and the Glossary for a description of the parameters
cited in this section.
• Verify that all ac service circuit breakers are Off or ac fuses are
removed.
• Verify that all output distribution circuit breakers are Off or output
distribution fuses are removed.
• If provided, verify that the LVD unit (BSP2 or BSP2C) and the
control unit are seated firmly in the initial shelf.
• Remove the distribution unit (BSP2 or BSP2C) cover.
• Verify that the battery, if installed, is disconnected.