WARNING: Below is a set of environmental conditions that must be met prior to installing
Megapixel VR products. The installation and/or use of products in these environments not
meeting these conditions may void all warranties.
Installation locations must be free of moisture.
Installation locations must be dust free.
All heavy and dirty site work must be complete. This includes re-working or
modications to walls, ceiling and oor.
All construction materials and debris must be removed, area swept, vacuum cleaned,
and the oor wet-mopped.
Building structure, roof, and walls are sealed and weather proofed. Roof successfully
tested for leaks.
Outside drainage system and oor drains checked and tested to protect the
equipment from ooding.
Floors sealed and cleaned.
All doors and windows installed and operational with weather seals.
All nal wall preparation complete including all taping, joint compound and re
sealant. Walls to be primed and nish painted.
Overhead re sprinkler or suppression system installed and pressure tested.
HVAC ducts blown free of debris. HVAC shall be operational/balanced and running
72 hours prior to equipment installation.