TILLER HANDLE
90-828631R3 MARCH 1999 Page 7B-11
15. Pull the throttle cables and wiring into the bracket.
16. Fasten arm with cover.
Arm Cover Screw Torque
135 lb-in. (15.3 Nm)
CAUTION
Wiring passing through the hand grip opening must be protected from chaffing or
being cut, by using the wiring conduit described in the following steps. Failure to
protect wiring as described could result in electrical system failure.
17. Place the throttle cables through the hand grip opening as shown.
18. Place all wiring
inside the wiring conduit.
19. Route the wiring through the hand grip opening and position the wiring conduit inside
the opening so that at least 1/2 in. (12.7 mm) extends inside the handle grip.
20. Push the wiring and throttle cables down into the handle grip and hold in place with two
clips.
1/2 in. (12mm)
1/2 in. (12mm)
a
b
b
d
c
a-Wiring Conduit (Place all Wiring Inside – See CAUTION above)
b-Place Wiring Conduit inside opening 1/2 in. (12.7 mm)
c-Throttle Cables (Position toward outer side)
d-Clips (2)

Table of Contents

Other manuals for Mercury 45

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Mercury 45 and is the answer not in the manual?

Mercury 45 Specifications

General IconGeneral
Horsepower45 HP
Cylinders3
StartingElectric
Full Throttle RPM Range5000-6000 RPM
SteeringRemote
ExhaustThrough Prop
Shaft Length20 in