7 Operation at Use of a PC
7.6 Example of a Parameterization and Measured Value Evaluation for SENTRON PAC5200
186 SENTRON PAC5100/5200, 7KM5212/5412, Device Manual
E50417-H1040-C568-A1, Edition 03.2015
7.6.3 Parameterization as Defined by the Task
Requirements
SENTRON PAC5200 is electrically connected to the system and commissioned as described in
Commissioning. Rated voltages and currents at the measuring inputs are switched off.
Parameterization
Start the user interface as described in Initial Start of the Operation (initial startup) or Starting the User
Interface during Operation (start during operation). Use the factory-preset IP address for this purpose.
On the Configure tab, configure the element AC measurement (see AC Measurement) according to the
following topology specifications:
Figure 7-73 Configure Tab, AC Measurement Example
NOTE
If you change settings in tabs, click Send on each tab to confirm the new setting. The settings are activated
only after the entire parameterization has been completed.