Advanced commissioning
7.2 Inverter control
You obtain the interconnection as in the example above, if you configured the interfaces of
the inverter with p0015 = 7 in the basic commissioning, also see Section Connections and
cables (Page 40).
An overview of all the parameters that belong to the command data sets is provided in the
List Manual.
Note
The converter requires approx. 4 ms to switch over the command data set.
Advanced settings
To change the number of command data sets in STARTER, you must open your STARTER
project offline.
You can edit command data sets if, in the STARTER project tree, you select "Configuration".
If you require more than two command data sets, then add command data sets using this but-
ton or remove them.
,
To simplify commissioning several command data sets, under the "Command data sets" tab
there is a copy function.
Figure 7-8 Editing command data sets in STARTER
Parameter
Description
p0010 = 15
Drive commissioning: Data sets
p0170
Number of command data sets
(factory setting: 2)
p0170 = 2, 3, or 4
p0010 = 0
Drive commissioning: Ready
r0050
Displaying the number of the CDS that is currently active
p0809[0]
Number of the command data set to be copied (source)
p0809[1]
Number of the command data set to which the data is to be copied (target)
p0809[2] = 1
Copying is started
Once copying has been completed, the inverter sets p0809[2] to 0.
p0810
Command data set selection CDS bit 0
p0811
Command data set selection CDS bit 1
r0050
Displaying the number of the CDS that is currently active
Converter with control units CU240D-2
128 Operating Instructions, 04/2015, FW V4.7.3, A5E34262100B AB