Commissioning
5.3 Basic commissioning with IOP
5.3
Basic commissioning with IOP
Commissioning a 1FK7 encoderless synchronous motor
If you want to operate the inverter using a 1FK7 encoderless synchronous motor, we
recommend using the STARTER for commissioning.
Basic commissioning wizard
The Basic Commissioning wizard detailed below is for Control Units with version 4.4
software or higher.
Procedure
For performing the basic commissioning of the converter with the IOP operator panel,
proceed the following steps:
1.
Select "Basic Commissioning..." from the Wizards
menu.
2.
Select "Yes" or "No" to a factory reset.
The factory reset is performed prior to saving all the
par
ameter changes that have been made during the
basic commissioning process.
3.
Select the Control Mode for the attached motor.
4.
Select the correct Motor Data for your Inverter and a
t-
tached motor.
This data is used to calulate the correct speed and di
s-
played values for the application.
Converter with control units CU240D-2
70 Operating Instructions, 04/2015, FW V4.7.3, A5E34262100B AB

Table of Contents

Related product manuals