Procedure
Proceed as follows to carry out basic commissioning:
1.
Select the control mode.
See also Section:
Selecting the control mode (Page 68)
2.
Select the I/O configuration to preassign the inverter interfaces.
The possible configu
rations can be found in sections:
Factory settings of
the inputs and outputs
(Page 50) and Default settings of inputs and out-
puts (Page 51).
3.
Set the applicable motor standard and the inverter su
pply voltage.
Select the application for the inverter.
"[0] Load cycle with high overload for applications requiring a high
dynamic performance, e.g. conveyor systems.
"[1] Load cycle with low overload ..." for applications that do not
require a high dynamic performance, e.g. pumps or fans.
[6], [7]: Load cycles for applications with encoderless 1FK7
synchronous motors.
4.
Select your motor.
5.
Enter the motor data according to the rating plate of your motor.
If you have selected a motor based on its article number, the data ha
s
already been entered.
6.
Set the most important parameters to suit your application.
7.
Technological use:
[0]: In all applications that do not fall under [1][3]
[1]: Applications involving pumps and fans
[2]: Applications with short ramp-up and ramp-down times. However,
this setting is not suitable for hoisting gear and cranes/lifting gear.
[3]: Setting only for steady-state operation with slow speed changes.
We recommend setting [1] if load surges in operation cannot be ruled
out.
Converter with control units CU240D-2