SMA Solar Technology AG 4 Starting and Stopping the System
Operating Manual SI60H-80H-BE-en-20 17
4 Starting and Stopping the System
4.1 Switching on the Sunny Island
Requirements:
The load-break switch in the DC cable must be closed.
The Sunny Island must not have switched itself off (see Section9.6 "Charging the Battery after Automatic Shutdown
in Off-Grid Systems", page69).
Procedure:
For systems with one Sunny Island, press the "On" button on the
Sunny Island.
For systems with up to three Sunny Island inverters, press and hold
the "On" button on the master until an acoustic signal sounds.
For multicluster systems, press and hold the "On" button on each
master until an acoustic signal sounds.
The inverter LED on each Sunny Island is glowing orange and the Sunny Island inverters are in standby mode.
4.2 Starting the System
Requirement:
All Sunny Island inverters must be switched on.
Procedure:
Press and hold the Sunny Island start-stop button until and acoustic
signal sounds.
or
Press and hold the button on the Sunny Remote Control until an acoustic signal sounds.
The inverter LED on each Sunny Island is glowing green.