SMA Solar Technology AG 9 Troubleshooting
Operating Manual SI60H-80H-BE-en-20 59
9.4.8 External Device and Component Category (8xx)
W 793 TimeOutDspSlv1 1 Time for performing a particular task
has been exceeded.
Contact the SMA Service Line.
W 794 TimeOutDspSlv2 1
W 797 AiVtgMonFailSlv1 1 Monitoring of the utility grid has
failed.
Contact the SMA Service Line.
W 798 AiVtgMonFailSlv2 1
No. Name Level Cause Corrective measures
F 801 Box 4 Plausibility check of the
contactors in the Multicluster
Box has failed.
Contact the SMA Service Line.
W 805 BoxNoGn 1 Operation with the generator
is not possible.
Reset the off-grid system. For this,
disconnect all loads, AC sources,
generator and DC sources. Open the
load-break switch of the BatFuse. Wait ten
minutes and restart the off-grid system.
Wait until all AC sources are feeding into
the stand-alone grid and all loads are
connected before connecting the
generator.
Contact the SMA Service Line.
F 806 BoxType 4 Configuration of the Sunny
Island does not match the
Multicluster Box.
Check whether the value of the parameter
250.23 Box matches the Multicluster
Box. If the value does not match, restart
the QCG (see installation manual of the
Sunny Island).
Contact the SMA Service Line.
W 807 BoxGdVtg 1 Voltage of the external energy
source is not within the valid
limiting values for connection.
Acknowledge the error (see Section9.2,
page41).
Contact the SMA Service Line.
F 809 BoxNoLod 4 Load-shedding contactor Q5
in the Multicluster Box is not
functioning correctly.
Reset the off-grid system. For this,
disconnect the off-grid system and restart.
The configuration may be incorrect.
Start the QCG and reconfigure
multicluster operation (see installation
manual of the Sunny Island).
Contact the SMA Service Line.
F 810 Box15V 4 15 V voltage supply in the
Multicluster Box is defective.
Contact the SMA Service Line.
F 811 Box24V 4 24 V voltage supply in the
Multicluster Box is defective.
Contact the SMA Service Line.
No. Name Level Cause Corrective measures