4-4
4.3 Installation of the machine.
4.3.1 Have the machine set onto the fastening bolts of the crate base.
(1) Tools
Sling, lifting equipment, spanner, movement plate, insertion blocks and level
adjusting blocks.
(2) Procedure
a.
After dismantling the wooden crate, get the manuals and tool box out.
b.
Remove the fastening bolts.
c.
Hook it using sling, lift it up and move to site for installation.
d.
Align the ground bolts and the base bores and set the later onto them.
Meanwhile, have the level adjusting blocks inserted to the underneath of the level
Remove the lifting equipment and slings.
f. Have nuts for the ground bolts mounted.