F3200 Operator's Manual Document No: LT0119
Placing Into Operation
Page 9-4 29 July 2002 Issue 2.04
COMMISSIONING CHECKLIST (CONTINUED)
3. POWER SUPPLY
A) Mains Wired correctly, MOV, cap fitted
B) "Mains Isolate Switch" and "NAE" label fitted
C) Mains Earth wired to stud, good contact
D) All 6 fuses fitted to MAF/PSU
E) Mains Switch neon off/on for switch off/on
F) MAF/PSU Mains On LED on, Fuse Blown LED off
G) VRECT at DC IN tab 40-42Vdc
H) Charger Voltage 27.3-27.4V warm, 27.5-27.6V cold
4. OPERATION
A) LEDs bright through window, "MAINS ON" LED on
B) Correct modules are configured and found on Init
C) Buzzer louder with microswitch operated
D) Controller LK7 in "Protect" position
E) LCD contrast correct for front view
F) De-isolate zones, system test pass on all zones
G) FIP MCP Programmed to Zone 1; Other: OK
H) "ALM" LED flashes & buzzer pulses for MCP operation
I) Acknowledge silences buzzer, Zone Resets
SERIAL NUMBER TEST PASSED
DATE: SIGNATURE