Disassembly/Assembly Mobile Generator
88 wc_tx000575gb.fm
9.7 Replacing the Generator
See Graphic: wc_gr003322
This procedure requires an appropriate crane capable of lifting 365 kg
(800 lbs.).
Removal:
9.7.1 See section Preparing Unit for Generator Removal.
9.7.2 Remove the screens (a) from both sides of the generator housing.
9.7.3 Remove the screws (b) that secure the shock mounts to the frame.
9.7.4 Support the engine from underneath and the generator from above.
9.7.5 Remove the screws (c) that mount the flex plates to the engine.
Reposition the flex plates by turning the generator fan.
9.7.6 Remove the screws (d) that secure the generator to the engine.
9.7.7 Using an appropriate crane or hoist, lift the generator up and away
from the engine.
Installation:
9.7.8 Position the generator into the frame.
9.7.9 Using Loctite 231 or equivalent on the screws (d), secure the
generator to the engine. Torque the screws to 69Nm (50 ft.lbs.).
9.7.10 Using Loctite 231 or equivalent on screws (c), secure the flex plates to
the engine. Torque the screws to 45 Nm (33 ft.lbs.); 35Nm (25 ft.lbs.)
on G 25 models.
9.7.11 Using screws (b), secure the shock mounts to the frame.
9.7.12 Secure the screens (a) to both sides of the generator housing.
9.7.13 Reconnect all wiring.
9.7.14 Reinstall the control panel enclosure and the roof.

Table of Contents

Other manuals for Wacker Neuson G 85

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Wacker Neuson G 85 and is the answer not in the manual?

Wacker Neuson G 85 Specifications

General IconGeneral
BrandWacker Neuson
ModelG 85
CategoryPortable Generator
LanguageEnglish

Related product manuals