■ Connection procedure for frames R6 to R9
Note: For frames R6 to R9 with option +H358, see also ACS880-01, ACS580-01,
ACH580-01, ACQ580-01 UK gland plate (+H358) installation guide (3AXD50000034735
[English]).
1. Remove the front cover: For IP21 drives: Release the retaining clip with a screwdriver
(a) and pull the cover by the bottom outwards (b).
2. For IP21 drives: Remove the cable entry box cover by undoing the mounting screws.
3. Attach the residual voltage warning sticker in the local language next to the control
unit.
4. Remove the side plates of the cable entry box by undoing the mounting screws.
5. Remove the shroud on the power cable terminals by releasing the clips on the sides
with a screwdriver and lifting (a). Knock out holes for the cables to be installed (b).
6. If parallel cables are installed (frames R8 and R9): Knock out the shrouds on the
power cable terminals for the cables to be installed.
7. Prepare the ends of the input power and motor cables as illustrated in the figure.
The bare shield will be grounded 360 degrees under the clamp.
8. Cut adequate holes into the rubber grommets (a). Slide the grommets onto the
cables. Slide the cables through the holes of the bottom plate and attach the
grommets to the holes (b).
9. Tighten the clamp onto the stripped part of the cable. Mind the sharp edges.
10. Attach the twisted shields of the cables under the grounding clamps.
11. Connect the phase conductors of the input cable to the L1, L2 and L3 terminals and
the phase conductors of the motor cable to the T1/U, T2/V and T3/W terminals.
Tighten the screws to the torque given in the figure.
102 Electrical installation – IEC