General
The following shouold be taken in consideration when running a robot in a water jaet 
application cell.
Never switch off the overpressure in motors and serial measurement compartment during 
cooling down of robot after it has been switched off.
To reduce the risk for corrosion due to condensation in gearboxes, it is recommendable that 
the robot is running with high speed on each axes at least on one occasion each hour. This is 
to lubricate the gearbox cavities.
When turning off an cleaning cell we recommend that the humid air is ventilated out from the 
cell, to avoid that the humid air is sucked into e.g gearboxes due to the arised vacuum when 
cooled down.