Site Preparation
7705 SAR-8 Installation Guide Page 65
Notes: (continued)
To provide necessary stability, ensure that the equipment rack is bolted to the floor. Ceiling
brackets are useful to provide additional stability.
The equipment rack must be properly grounded.
Install components after the chassis is installed in the rack.
Maintain a clearance of at least 2.5 in. (6.4 cm) at the front of the router for cable
management.
Maintain a clearance of at least 3 in. (7.6 cm) on each side to ensure adequate air intake
and exhaust. When mounting the router in a rack, ensure that the rack complies with all
requirements outlined in
Chassis Location Requirements on page 72.
The 7705 SAR-8 includes factory-installed rack-mounting brackets to mount in a 19-inch
equipment rack.