Installing the Components
7705 SAR-8 Installation Guide Page 107
b) Alternatively, the panel may be grounded to the rack through its mounting screws
while adhering to the following requirements.
→ All surfaces that are used for intentionally grounding the panel must be brought
to a bright finish, and an antioxidant solution must be applied to the surfaces
being joined.
→ Non-conductive coatings (such as lacquer and enamel) must be removed from
threads and other contact surfaces to ensure electrical conductivity. Thread-
forming screws with paint piercing washers may be used for this purpose during
installation.
Disconnecting a 1.0/2.3 Mini-Coaxial Cable from a
Distribution Panel
Some installations have the 1.0/2.3 Mini-Coaxial Distribution panel installed with no rack
space between the equipment above and below the panel. This type of installation may
require the use of a disconnection tool to facilitate the removal of a mini-coaxial cable.
Figure 30 shows the tool (top and side views). Figure 31 illustrates the use of the tool, which
is shipped with the distribution panel.
Tool required:
• disconnection tool for 1.0/2.3 mini-coaxial connectors (supplied with panel)
Figure 30: Mini-Coaxial Connector Disconnection Tool
Figure 31: Disconnecting a 1.0/2.3 Mini-Coaxial Cable from a Distribution Panel