Connecting External Cables
asafeinstall_dgb, AutroSafe Interactive Fire Detection System, Release 4,
116-P-ASAFE-INSTALL/DGB, Doc-1004796-2, 2021-08-23, Autronica Fire and Security AS
Page 50
10.11 Mains Power Connections
10.11.1 Power Cabinet STX
The installation instructions from the supplier has to be followed, and the
manual can be found following the links in the table below.
http://product.autronicafire.com/products/fire-and-gas-detection-
systems/fg-system-units/power-supply-
http://product.autronicafire.com/products/fire-and-gas-detection-
systems/fg-system-units/power-supply-units/stx-5a/
http://product.autronicafire.com/products/fire-and-gas-detection-
systems/fg-system-units/power-supply-units/stx-10a/
10.11.2 Power Supply BPS-410
Indicates the presence of a hazard that will or could cause personal
injury or property damage if ignored
Power must not be applied before commissioning, refer to
Commissioning Handbook.
When applying power during commissioning, always connect the cables
to the batteries in the power cabinet first, then power up the system
shortly afterwards by connecting the mains cable to a mains socket
(230V/115V AC) or by switching the power ON from an external main
fuse box.
Note that the isolation must be kept on the mains cable as close up to
the terminal points (L, N and ) as possible.