7850-Install-IG101 Installation Guide
Brocade
®
7850 Extension Switch Hardware Installation Guide
NOTE
If Virtual Fabrics (VF) is enabled, you need to use the configupload -vf command only once to upload
configuration for the virtual fabric (all logical switches configured on the device). For more information, refer
to the discussion of configupload/download in the Brocade Fabric OS Administration Guide.
Powering Down the Device
Perform the following steps to power down the device:
1. Shut down the Fabric OS software using the sysShutdown command.
2. Unplug the power cables from the power source to power off before servicing the device or FRUs.
All devices are returned to their initial state the next time the switch is powered on.