Install the Pedestal
Mount and Level the Pedestal
1. Ensure the concrete has been prepared with according to the Bolt Pattern Template (PN: 75-
001163-01). This includes:
Four bolts set into concrete with two nuts and two washers for each bolt with the bolt
extending 63.5 mm (2 1/2 in) above the surface
Conduit stub-up measuring approximately 0.3 m (1 ft) above the concrete surface
Approximately 1.5 m (5 ft) of service wiring extending above the concrete surface
2. Remove the top nut and top washer from each of the four bolts
in the pad.
3. Place the pedestal over the conduit, routing the service wiring
through the column. Ensure the edge with the cut-out for the
CMK is located in the back of the station.
4. Adjust the lower nuts to ensure the pedestal is level.
5. When level, fasten the pedestal to the bolts using the washer
and nut removed from the bolt. Torque the top nuts to 122 Nm
(90 ft-lbs).
Important: Verify the pedestal is level and plumb after
each adjustment by positioning the level at various
locations on the base plate and on the pedestal.