CVC TECHNOLOGIES, INC. CVC 400 OPERATION MANUAL
10. OPERATION INSTRUCTION
a. Ensure that electric supply and compressed air are properly connected.
b. Ensure that the HHT Control panel plug is properly connected to the HHT socket on the machine.
c. It is necessary to adjust the machine working parts to a proper position according to the product to
be labeled and the label to be applied. (Refer to chapter 11 Machine Adjustments.)
10.1 Air Regulator Set Check (Optional)
Open the shutoff valve on the air regulator, and check that the air pressure displayed on the air gauge
is at 5 bars. If necessary, adjust the air pressure adjustment knob by pulling it up and rotate it to
around 4~5 kgf/cm
2
. If no compressed air is available, check if the air compressor and ensure that
the valve is open, if no abnormality is found, the air regulating set may be required repairing or
replacement.
Air pressure
gauge
Shutoff valve
Pull up
Air pressure adj. knob
Air inlet
Air outlet
Fig.10.1-1
10 - 1