9. PREPARATION BEFORE OPERATION
9.1 Inspection before Operation
9 - 1
Ensure that no foreign objects or tools are left in the machine.
Ensure that air and power supply are normal.
Check that there are no loose or damaged parts in the machine.
If any of the stated abnormality is observed, turn off the machine and carry out a service
of the machine to fix the problem before restarting the machine.
Always switch off the machine power before mounting labeling mechanisms or label rolls.
9.2 Installing the Label Web
Labels will not dispense if label web is threaded incorrectly.
9.2.1 Label Rolled Position
a. Label rolled outside (Copy Positions 1,2,3,4 of Label Position Chart., Fig 9.3.5)
Fig.9.2.1-1

Table of Contents