D 4.7 18
D_4.7_01_GB.fm 18-34
1.6 Interrupting/terminating operation
During breaks (e.g. the material supply
truck is late)
- Determine the approximate duration.
- When cooling down of the material be-
low the minimum paving temperature
must be expected, run the paver fin-
isher finisher empty and create an
edge like the end of a layer.
- Set the drive lever (1) to the center po-
sition.
During extended interruptions
(e.g. lunch break)
- Drive lever (1) into centre position,
RPM speed adjustment (2) to mini-
mum position.
- Switch off ignition.
- Switch off screed heater (system).
- When screed is operated with the op-
tional gas heating system, close the valves of the bottles.
A
The screed must be heated up to the correct paving temperature before paving may
be restarted.
2
1
Element2_konv_Rad_656.bmp/Element3a_konv_Rad_656.bmp/