Figure 18 Installing blade enclosure 1
Install Control Stations and the extension cables
The primary Control Station (CS0) will slide into the slot above the last installed blade
enclosure.
Note
Ensure that you install the primary Control Station (CSO) before installing CS1. Refer to
the location of CS0 when you removed it as shown in Installation order of system
components on page 28.
Assemble components in your cabinet
Install Control Stations and the extension cables 35