Expected load
Expected Load
Unit 1 .. 8
The load which you expect the unit will bear during the lifting operation.
Protections (overload, preload) are based on this value.
X Value,
Y Value
Enter the physical location of the units w.r.t. each other, to enable the
system to calculate the COG of the whole system.
- You can define the zero-point of the grid where you want since only
the respective distances of the units are relevant.
- The numbers of the units are used in the COG All units screen:
Expected COG
The X/Y position where you expect the COG to be located.
It’s displayed on the COG All units window.
(top view)