4. Commissioning
4-28
Festo P.BE-SPC11-SYS-ASI -EN en 0203NH
4.4.1 Switch-on behaviour after successful commissioning
If commissioning has already been carried out, the SPC11 is
ready to operate after a few seconds.
Start: Switch-on
behaviour
Display of
system parameters
Display of
amplification stage
Display of
cushioning stage
Position
P.01 or P.02?
SPC11 is ready to operate.
Theaxisispressedactively
intothe endpositionandwaits
for the positioning t ask.
SPC11 is ready to operate.
The axis stands uncontrolled
and waits for the positioning
task.
Yes No
Wait approx. 1 second
Wait approx. 1 second
Wait approx. 1 second
Current value
Current value
Current value
Firmware version
number
Display of
firmware version
Wait approx.0.5 second
Fig. 4/5: Switching-on behaviour of the SPC11 after commissioning

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Festo Soft Stop SPC11 Series and is the answer not in the manual?

Festo Soft Stop SPC11 Series Specifications

General IconGeneral
BrandFesto
ModelSoft Stop SPC11 Series
CategoryControl Unit
LanguageEnglish

Related product manuals