Powering On
This section explains how to turn on the ETERNUS DX.
To turn on the ETERNUS DX, perform the following procedure.
Via the power switch
Press the Power switch to turn on the
ETERNUS DX.
The following methods can be used to turn the power on by linking with the server.
Power Synchronized Unit
Use the power synchronized unit to turn on the ETERNUS DX.
Wake On LAN
Use the Wake On LAN function to turn on the power.
Note
Before turning on the
ETERNUS DX, make sure that the main line switches of the power distribution units
and the PSU switches on the power supply units of the ETERNUS DX are "ON". Do not turn the main line
switches of the power distribution units and the PSU switches on the ETERNUS DX to the OFF position.
IMPORTANT
The following table shows the time required for the
ETERNUS DX to reach the READY state (the READY
LED turns on) after turning the power on. This should be taken into consideration for scheduled
operations.
Table 1 Time Required to Turn the Power On
Model
Deduplication/
Compression function
is disabled
Deduplication/
Compression function
is enabled
Unified configuration (*1)
VLAN/Bonding maximum
configuration
Normal Error Normal Error Normal Error Normal Error
DX60 S5 Approx. 5
minutes
Max. 18
minutes
DX100 S5 Approx. 5
minutes
Max. 18
minutes
Approx. 10
minutes
Max. 40
minutes
Approx. 20
minutes
Max. 50
minutes
DX200 S5 Approx. 5
minutes
Max. 18
minutes
Approx. 9
minutes
Max. 22
minutes
Approx. 10
minutes
Max. 40
minutes
Approx. 20
minutes
Max. 50
minutes
DX500 S5 Approx. 5
minutes
Max. 18
minutes
Approx. 12
minutes
Max. 25
minutes
Approx. 10
minutes
Max. 42
minutes
Approx. 22
minutes
Max. 53
minutes
DX600 S5 Approx. 7
minutes
Max. 20
minutes
Approx. 15
minutes
Max. 28
minutes
Approx. 12
minutes
Max. 44
minutes
Approx. 24
minutes
Max. 55
minutes
DX900 S5
(*2)
Approx. 10
minutes
Max. 20
minutes
Approx. 14
minutes
Max. 24
minutes
*1: The time required to turn the power on for the Unified configuration depends on the NAS configuration (or the number of
shared folders and the number of VLAN/Bonding configurations).
*2: The ETERNUS DX900 S5 supports the Compression function only.
Before turning the server on, check that the
ETERNUS DX and the network devices that connect the
ETERNUS DX and the server are all in READY status.
If the server is turned on while any of these devices are not in READY status, the server may not be able
to recognize the ETERNUS DX.
1. Basic Operation
Powering On and Off
18 Operation Guide (Basic)

Table of Contents

Other manuals for Fujitsu ETERNUS DX S5 Series

Related product manuals